More Delays at Finnish Nuclear Plant


Comment: The UN supports Nuke Power as being CO2 free, REALLY, they are wrong! Just say NO to France's Nuke Power and all nuke power! Nuke power is not CO2 free, building the Nuke Plant is full of CO2 (trucks, the power contractors are using), uranium mining and milling, trucking the yellowcake to a uranium processing plant, ETC, not CO2 free. In addition, uranium mining has never been done safely anywhere in the world! Just say no to France nuke power, wake up Virginia and Maryland, we do not want nuke power! Oh, yea, I listed some good comments from the article (names not included)!

Henna Aaltonen for The International Herald Tribune
The Olkiluoto nuclear power plant in Finland is facing more delays.

September 2, 2009, 8:04 am
By James Kanter

Areva, a French nuclear construction company, said this week that its project to build the world’s most powerful reactor remained mired in delays and was over-budget by 2.3 billion euros, or about $3.3 billion.

The price tag of the plant in Olkiluoto, Finland — the first of a fleet of so-called evolutionary power reactors that Areva foresees building in coming years — was about $4.3 billion in 2003 and costs have steadily increased.

The reactor was meant to have gone online early this summer but Areva no longer is committing to any dates for its completion. Patrice Lambert de Diesbach, an energy analyst with CM-CIC Securities in Paris, said the latest developments were “bad news” for Areva and “should be sanctioned by the market.”

The problems faced by Areva are important a time when the nuclear power industry is promising to build safer and more reliable reactors than during the last building boom in the 1960s and early 1970s. Interest in the sector is high again as governments seek sources of electricity that, like nuclear fission, emit little or no carbon dioxide and that cut down on reliance on fossil fuels like coal.

Areva has blamed the Finnish utility company, Teollisuuden Voima, which ordered the reactor, for the delays.

But the Finnish safety authority has said that Areva outsourced a number of aspects of the construction to unqualified subcontractors, making it responsible for a number of the problems.

Whatever the reasons, a key question raised by the project is whether the industry can build enough power plants on time – and on budget – to make a significant contribution to lowering greenhouse gases within the time periods that have been recommended by United Nations scientists and agreed by governments.

So far there are few signs of a breakthrough in Finland.

Areva said this week that it would not begin work on the final stages of the reactor until the Finnish utility agreed to a new set of proposals and modifications.

Comments:

Link

2. September 2, 2009, 9:55 am

Link
When all the dust settles and we aren’t arguing about environmental issues, nuclear energy is still a big messy business even after all these years and with France’s supposed “experience”.

The bottom line is, nukes are a really hard way to make energy.

— Mark

3. September 2, 2009
10:01 am

Link
I think the NRC would be completely irresponsible if it gave any further consideration to the application for a new reactor at Calvert Cliffs in Maryland if the current contractors are involved. There appear to be serious safety issues involved in this fiasco.

— Chris

http://greeninc.blogs.nytimes.com/2009/09/02/more-delays-at-finnish-nuclear-plant/

Sunday, August 30, 2009

Safety procedures in disarray at Finland’s Olkiluoto 3 nuclear construction site

COMMENT: Please review the two articles about the problems of the so call "New Nuke Plant Design" and the problems with the French Nuke Bunch! Demand Virginia to stop doing business the French Nuke Connection before they ruin our state with high price nuke plants and their further goals of uranium mining!

Posted by Justin on August 13, 2008 9:00 AM

Documents seen by Greenpeace show that French company Areva is failing to implement vital safety procedures in the troubled construction of its prototype European Pressurized Water Reactor (EPR) in Olkiluoto, Finland. As well as being 2-3 years behind schedule, 70 per cent over budget, and experiencing 1,500 construction defects along with a damaging fire, the reactor’s safety cannot be guaranteed.

The documents show that, during the construction of the steel framework in the base of the the world's largest nuclear reactor, welders had no specifications as to how the welding should be properly performed for an entire year and, furthermore, tests to ensure the quality of the welding have not been carried out.

Bouygues, an Areva sub-contractor, has had no qualified welding supervisors at the site for over a year and still does not have any. Staff are given a mere two weeks’ training instead of having the international standard university degree. The company also listed people who had not worked in the role as welding supervisors.

Areva, the Finnish nuclear safety authority STUK, and the country’s electricity generator TVO have all been aware of these problems and yet the necessary vital safeguards have not been implemented. Poor welding could cause or exacerbate a nuclear accident – both the reactor cooling system and the reactor itself are mounted on the steel framework. If this is how the construction has proceeded so far, what can we expect when it comes to the installation of reactor components or electronic safety systems?

Nuclear safety expert Dr Helmut Hirsch states that there is a ‘bad safety culture’ at the Olkiluoto 3 site, calling into question the durability of the steel structure and its ability to withstand electrochemical corrosion.

Parts of Olkiluoto 3 affected by the violations

To make matters worse, this is history repeating itself. Lessons have not been learned. Inspections on the construction of the other EPR at Flamanville in France found that a quarter of the welding in the reactor’s steel lining was substandard. Cracks were also found in the reactor’s concrete base. When the problem was discovered, it was sub-contractor Bouygues again at the root of the shortcomings and construction was halted by French nuclear watchdog ASN.

How has all this happened? It looks as if these potentially catastrophic shortcomings in Finland have arisen from the parties seeking to cut corners on rocketing construction costs. Quality standards agreed in contracts between Areva and TVO are poor. Contractual requirements for the competence of welding staff look to have been breached. STUK and TVO have failed to deal with safety violations. TVO has also failed to use sanctions such as stopping construction so that failures could be addressed. It all adds up to a recipe for disaster.

It is clear that there can be little public confidence in the construction of the Olkiluoto 3 nuclear reactor. How and why are we to believe assurances on matters of safety from the likes of Areva now and in the future? This is yet another blow to the public relations distortion that nuclear energy is safe. The industry has shown itself - again - to be anything but open and honest in its dealings with the public.

None of us would dream of flying in a plane, driving a car, or living in a house which we knew to be built to such shockingly poor standards of construction, supervision and safety. So why should we tolerate or allow such attitudes, incompetence and deception in the construction of a nuclear facility which, in the event of an accident, could cause massive, unquantifiable damage to our health and the environment? The answer is simple: we can not and we should not.

Areva and its sub-contractors should be reminded whose interests they truly serve. Public safety should always be put before profit and poor procedures. Those responsible for this misconduct should be held to account. The construction of Olkiluoto 3 must be halted.

http://weblog.greenpeace.org/nuclear-reaction/2008/08/breaking_news_safety_procedure.html

In Finland, Nuclear Renaissance Runs Into Trouble

Published: May 28, 2009

OLKILUOTO, Finland — As the Obama administration tries to steer America toward cleaner sources of energy, it would do well to consider the cautionary tale of this new-generation nuclear reactor site.

Henna Aaltonen for The International Herald Tribune

After four years of construction and thousands of recorded defects and deficiencies, the price tag on the reactor in Olkiluoto, Finland, has climbed at least 50 percent.

Henna Aaltonen for The International Herald Tribune

Jouni Silvennoinen, the project manager of the ambitious Olkiluoto nuclear plant. The reactor’s design was supposed to make it cheaper and faster to build, and safer, than older plants.


A blog about energy, the environment and the bottom line.

Go to Blog » The massive power plant under construction on muddy terrain on this Finnish island was supposed to be the showpiece of a nuclear renaissance. The most powerful reactor ever built, its modular design was supposed to make it faster and cheaper to build. And it was supposed to be safer, too.

But things have not gone as planned.

After four years of construction and thousands of defects and deficiencies, the reactor’s 3 billion euro price tag, about $4.2 billion, has climbed at least 50 percent. And while the reactor was originally meant to be completed this summer, Areva, the French company building it, and the utility that ordered it, are no longer willing to make certain predictions on when it will go online.

While the American nuclear industry has predicted clear sailing after its first plants are built, the problems in Europe suggest these obstacles may be hard to avoid.

A new fleet of reactors would be standardized down to “the carpeting and wallpaper,” as Michael J. Wallace, the chairman of UniStar Nuclear Energy — a joint venture between EDF Group and Constellation Energy, the Maryland-based utility — has said repeatedly.

In the end, he says, that standardization will lead to significant savings.

But early experience suggests these new reactors will be no easier or cheaper to build than the ones of a generation ago, when cost overruns — and then accidents at Three Mile Island and Chernobyl — ended the last nuclear construction boom.

In Flamanville, France, a clone of the Finnish reactor now under construction is also behind schedule and overbudget.

In the United States, Florida and Georgia have changed state laws to raise electricity rates so that consumers will foot some of the bill for new nuclear plants in advance, before construction even begins.

“A number of U.S. companies have looked with trepidation on the situation in Finland and at the magnitude of the investment there,” said Paul L. Joskow, a professor of economics at the Massachusetts Institute of Technology, a co-author of an influential report on the future of nuclear power in 2003. “The rollout of new nuclear reactors will be a good deal slower than a lot of people were assuming.”

For nuclear power to have a high impact on reducing greenhouse gases, an average of 12 reactors would have to be built worldwide each year until 2030, according to the Nuclear Energy Agency at the Organization for Economic Cooperation and Development. Right now, there are not even enough reactors under construction to replace those that are reaching the end of their lives.

And of the 45 reactors being built around the world, 22 have encountered construction delays, according to an analysis prepared this year for the German government by Mycle Schneider, an energy analyst and a critic of the nuclear industry. He added that nine do not have official start-up dates.

Most of the new construction is underway in countries like China and Russia, where strong central governments have made nuclear energy a national priority. India also has long seen nuclear as part of a national drive for self-sufficiency and now is seeking new nuclear technologies to reduce its reliance on imported uranium.

By comparison, “the state has been all over the place in the United States and Europe on nuclear power,” Mr. Joskow said.

The United States generates about one-fifth of its electricity from a fleet of 104 reactors, most built in the 1960s and 1970s. Coal still provides about half the country’s power.

To streamline construction, the Nuclear Regulatory Commission in Washington has worked with the industry to approve a handful of designs. Even so, the schedule to certify the most advanced model from Westinghouse, a unit of Toshiba, has slipped during an ongoing review of its ability to withstand the impact of an airliner.

The Nuclear Regulatory Commission has also not yet approved the so-called EPR design under construction in Finland for the American market.

This month, the United States Energy Department produced a short list of four reactor projects eligible for some loan guarantees. In the 2005 energy bill, Congress provided $18.5 billion, but the industry’s hope of winning an additional $50 billion worth of loan guarantees evaporated when that money was stripped from President Obama’s economic stimulus bill.

The industry has had more success in getting states to help raise money. This year, authorities permitted Florida Power & Light to start charging millions of customers several dollars a month to finance four new reactors. Customers of Georgia Power, a subsidiary of the Southern Co., will pay on average $1.30 a month more in 2011, rising to $9.10 by 2017, to help pay for two reactors expected to go online in 2016 or later.

But resistance is mounting. In April, Missouri legislators balked at a preconstruction rate increase, prompting the state’s largest electric utility, Ameren UE, to suspend plans for a $6 billion copy of Areva’s Finnish reactor.

Areva, a conglomerate largely owned by the French state, is heir to that nation’s experience in building nuclear plants. France gets about 80 percent of its power from 58 reactors. But even France has not completed a new reactor since 1999.

After designing an updated plant originally called the European Pressurized Reactor with German participation during the 1990s, the French had trouble selling it at home because of a saturated energy market as well as opposition from Green Party members in the then-coalition government.

So Areva turned to Finland, where utilities and energy-hungry industries like pulp and paper had been lobbying for 15 years for more nuclear power. The project was initially budgeted at $4 billion and Teollisuuden Voima, the Finnish utility, pledged it would be ready in time to help the Finnish government meet its greenhouse gas targets under the Kyoto climate treaty, which runs through 2012.

Areva promised electricity from the reactor could be generated more cheaply than from natural gas plants. Areva also said its model would deliver 1,600 megawatts, or about 10 percent of Finnish power needs.

In 2001, the Finnish parliament narrowly approved construction of a reactor at Olkiluoto, an island on the Baltic Sea. Construction began four years later.

Serious problems first arose over the vast concrete base slab for the foundation of the reactor building, which the country’s Radiation and Nuclear Safety Authority found too porous and prone to corrosion. Since then, the authority has blamed Areva for allowing inexperienced subcontractors to drill holes in the wrong places on a vast steel container that seals the reactor.

In December, the authority warned Anne Lauvergeon, the chief executive of Areva, that “the attitude or lack of professional knowledge of some persons” at Areva was holding up work on safety systems.

Today, the site still teems with 4,000 workmen on round-the-clock shifts. Banners from dozens of subcontractors around Europe flutter in the breeze above temporary offices and makeshift canteens. Some 10,000 people speaking at least eight different languages have worked at the site. About 30 percent of the workforce is Polish, and communication has posed significant challenges.

Areva has acknowledged that the cost of a new reactor today would be as much as 6 billion euros, or $8 billion, double the price offered to the Finns. But Areva said it was not cutting any corners in Finland. The two sides have agreed to arbitration, where they are both claiming more than 1 billion euros in compensation. (Areva blames the Finnish authorities for impeding construction and increasing costs for work it agreed to complete at a fixed price.)

Areva announced a steep drop in earnings last year, which it blamed mostly on mounting losses from the project.

In addition, nuclear safety inspectors in France have found cracks in the concrete base and steel reinforcements in the wrong places at the site in Flamanville. They also have warned Électricité de France, the utility building the reactor, that welders working on the steel container were not properly qualified.

On top of such problems come the recession, weaker energy demand, tight credit and uncertainty over future policies, said Caren Byrd, an executive director of the global utility and power group at Morgan Stanley in New York.

“The warning lights now are flashing more brightly than just a year ago about the cost of new nuclear,” she said.

And Jouni Silvennoinen, the project manager at Olkiluoto, said, “We have had it easy here.” Olkiluoto is at least a geologically stable site. Earthquake risks in places like China and the United States or even the threat of storm surges mean building these reactors will be even trickier elsewhere.

Matthew L. Wald contributed reporting from Washington.